Robnett Electric, Inc.

Current Projects

MTA Universal Fare System (UFS) OP-002

Installation of (155) Stand Alone Validators, and (303) Ticket Vending Machines (TVM’s). This installation includes the installation, terminating and testing of AC power, Cat-5, and multimode fiber optic cable. The UFS installation includes all MTA passenger stations (Redline, Blueline, Greenline, Pasadena Goldline, and Metrolink stations). The TVM’s on the Pasadena Goldline are currently operational. Robnett Electric. Inc. is the turnkey installation subcontractor.
Contr.:       Cubic Transportation Systems

MTA Retrofit of the METRO Red Line Segment One Gas Monitoring System Contract No. OP-3346-0642

Design/Build. Removal of the existing Methane gas detection equipment and the installation of methane and H2S sensors in (5) Redline stations. Sensors to be installed in all passenger stations and tunnels. Installation includes local and system wide testing.
Contr.:       Robnett Electric, Inc

MTA CO703 Bus Division2, 9, and RRC Lighting Upgrade

Design/Build. Design and installation of new lights at (3) MTA facilities.
Contr.:       Robnett Electric, Inc

MTA CO705 Bus Exhaust System at Division 2 & the RRC

Installation of power to Bus Exhaust Systems.
Contr.:       NS CORPORATION